Pre-Site Requirements
Hose / Spray Bar

Standards of Testing:
CWCT Standards for Systemised Building Envelops and Test Methods for Building Envelopes, December 2006.
Section 9, Section 10, BS EN 13051:2001, AAMA 501.2-15, NHBC Standards 2018 Chapter 6.9 S17 and NHBC Standards 2018 Chapter 6.9 S18.

The following online form must be completed in full.
Marked up elevation drawings will need to be submitted to:
andrew.mapley@lft.co.uk

Following completion accompanying documents should be sent to: andrew.mapley@lft.co.uk

Additional information required: Details of test specimen as follows: Type/s of construction, Profile references,
Origin of materials, Types of materials, Date/s of manufacture ( if known), Dimensioned drawings of the specimen and Product designation from manufacturers literature.

Note: Reports will be issued in a simplified format certificate. Unless otherwise requested.
Any information listed in BS EN ISO 17025:2017, 7.8 Reporting of results will be readily available and full format certificate can be provided at extra cost.

Technical Data for the system being tested is to be provided.
Where a re-test is being conducted, details of any remedial works must be specified and recorded with testers before tests commence.

All certificates of tests will be issued once payment has cleared.
Certificates will be ready to issue 5 days after testing has been completed.
An expedited service is available at extra cost.

A MARKED UP ELEVATION DRAWING AND UNMARKED ELEVATION DRAWING
MUST BE SUPPLIED VIA EMAIL.